I saw a comment from another site that a lot of the data center locations on this map aren’t accurate. Is there any truth to that?
2 comments

I was thinking some of the community ones are bogus and then I started looking closer at a few of the hotspots. There is what appears to be a compelling site for a datacenter right in the middle of a cluster of these reports:

https://maps.app.goo.gl/nZyt5Yb3kqxj5thc8

That marker may be a bit off. There was a proposed data center in Midtown College Station, rejected about 8 months ago. https://www.kbtx.com/2025/09/12/college-station-city-council...
I looked around North Dakota and there are several that say community reported. Pretty sure those either don't exist or aren't significant in size if they do exist.
They're possibly bitcoin mines.

https://www.governor.nd.gov/news/burgum-one-worlds-largest-d...

> WILLISTON, N.D. – Gov. Doug Burgum today announced the construction of one of the largest data centers in the world near Williston as North Dakota continues to emerge as a hub for high-performance computing, including cryptocurrency mining.

> The Atlas Power Data Center being built by FX Solutions Inc. is part of a $1.9 billion, multiyear project that will require more than 100 workers during the two-year construction period and create more than 30 permanent jobs, according to Richard Tabish, president of Missoula, Mont.-based FX Solutions. Atlas Power, an operator of high-density facilities serving cryptocurrency mining and high-performance computing utilizing alternative power generation, will own and operate the data center following its completion.

> ...

> The first phase of the project will consist of 16 buildings, each 350 feet long by 30 feet wide, to house tens of thousands of servers that will conduct high-performance computing using 240 megawatts of electricity. Phases 2 and 3 call for expanding to 500 megawatts and then 700 megawatts, adding additional buildings and servers.

And later...

https://kfgo.com/2023/06/25/williams-co-residents-frustrated...

> WILLISTON, N.D. (KFGO) – Residents west of Williston were hopeful for a few hours on Tuesday, June 20, after the Williams County Commission voted unanimously to instruct the local power co-op to shut off electricity in a portion of a local cryptocurrency mine. But Corey Seidel said he knew the effort had failed by nightfall, when the servers were still operating at their usual levels.