|
|
|
|
|
by mitthrowaway2
145 days ago
|
|
If you measure how long a hundred "3-day tasks" actually take, in practice you'll find a range that is about 2-12. The variance doesn't end up getting de-risked. And it doesn't mean the 3-day estimate was a bad guess either. The error bars just tend to be about that big. |
|
I'm not saying it never happens, but the whole reason for the planning poker process is to surface the things that might turn a 3 point story into a 13 point story, with everyone around the table trying to imagine what could go wrong.
You should not be getting 2-12 variance, unless it's a brand-new team working on a brand new project that is learning how to do everything for the first time. I can't count how many sprint meetings I've been in. That level of variance is not normal for the sizes of stories that fit into sprints.