Hacker News new | ask | show | jobs
by lhl 633 days ago
Runpod.io rents the next-gen MI300X's for $4/hr, although since they also rent H100's for $3/hr (that are easier to work with/faster for training) it might be more of a novelty.
1 comments

I thought the whole selling point of AMD GPUs was that they were a lot cheaper than Nvidia GPUs?
Cheaper for the cloud company. But that doesn’t always translate to cheaper for the end user. Maybe they cost more to run or maybe there’s fewer of them so they’re more expensive to book?
At least a couple years ago, a big advantage of Nvidea cards was how much cheaper they were to run power wise-often the dies that made it into cloud level cards would be binned consumer dies.

Not sure if that’s still the case, but I’d say it’s plausible.

Impossible. Power costs for H100-like cards are dwarfed by the cost of the cards themselves. H100 at full load will consume ~$3500 (rough estimate) of power in 5 years at $0.12/kWh.
Data centers are more constrained by availability of power, and the matching cooling, than the actual bulk cost of it.

For example, I've been in situations where we had to deploy fewer hard drives per server unit than we otherwise would have, just because we knew we couldn't power & cool the racks if we fully stocked them.

How much do you think it would cost to install cooling for 5kW power output (1 8xH100 node)?