[2019-07-10 20:13 UTC] During our investigation into the root cause of the first event, we identified a code path likely causing the bug in a new minor version of the database’s election protocol.
[2019-07-10 20:42 UTC] We rolled back to a previous minor version of the election protocol and monitored the rollout. There's a 20 minute gap between investigation and "rollback". Why did they rollback if the service was back to normal? How can they decide, and document the change within 20 minutes? Are they using CMs to document changes in production? Were there enough engineers involved in the decision? Clearly all variables were not considered. To me, this demonstrates poor Operational Excellence values. Your first goal is to mitigate the problem. Then, you need to analyze, understand, and document the root cause. Rolling-back was a poor decision, imo. |
Thanks for the questions. We have testing procedures and deploy mechanisms that enable us to ship hundreds of deploys a week safely, including many which touch our infrastructure. For example, we do a fleetwide version rollout in stages with a blue/green deploy for typical changes.
In this case, we identified a specific code path that we believed had a high potential to cause a follow-up incident soon. The course of action was reviewed by several engineers; however we lacked an efficient way to fully validate this change on the order of minutes. We're investing in building tooling to increase robustness in rapid response mechanisms and to help responding engineers understand the potential impact of configuration changes or other remediation efforts they're pushing through an accelerated process.
I think our engineers’ approach was strong here, but our processes could have been better. Our continuing remediation efforts are focused there.