by nonameface
4022 days ago
|
|
I did a hybrid for my first freelance. I charged hourly, but because I was new and unsure still in my skills (and had never actually set up what they were asking for before), I set a maximum upper bound for the client so they wouldn't be punished by my inexperience. For example I charged them $75/hr and estimated the job would take me 8 hours. ($600) I told them my fee was $75/hr with a maximum cost of 20 hours ($1500) needed to do the project. This gave them an upper bound for the maximum they would have to pay me so they could budget/get approval. The job was small enough that scope creep wasn't really an issue though. I ended up charging them $800 as I forgot to include travel time to their location. First estimate was remote. I charged them full $75/hr for my travel time. |
|