by Retric
1 day ago
|
|
That 3+:1 is actually from being pedantic. 2:1 implies 33% thermal efficiency to the grid which is commonly achieved in normal operations. Unfortunately engineering means you can’t work with such overly simplified models. Many ways of dumping heat run into issues from solar gain prevents dumping significant heat under the employe parking lot etc. |
|
In my experience we saw some losses when taken as a system that prevented us from hitting 2:1, but they weren't anywhere near 50%. We also ran closer to 40% than 33% thermal efficiency in the power generating loop, so many of the system thermal costs are baked into that 33% efficiency to the grid.
Basically, each reactor install will have it's own minor issues. Overall they should be hitting around 2:1 as an entire system. If they aren't there is something going on that I haven't come into contact with (which is quite a lot, I'm sure).