by beloch
24 days ago
|
|
This is one of the data centres that went to the extra expense of building a closed loop cooling system that would, supposedly, not waste water on a continuous basis. Apparently, even these are not so clean to set up. Governments are going to need to start paying more attention to the commissioning process apparently. -------- "Meta said that it's supporting its general contractor, Fortis, which stopped discharging and began hauling wastewater offsite" -------- Governments should also watch where this wastewater is being hauled to, and likely just dumped. |
|