by stonogo 2 hours ago
> Is it, though?

Yes.

There is no point in waiting for interconnection when you can just... not do that, and do all your generation behind the meter, with complete control of the generation to match your load. Solar wants an interconnect so they can sell off surplus; with gas you just turn the dial down to meet the load and walk away.

The clock is running on the datacenter goldrush. 70-90% of the capex window is going to be soaked up just with construction time. Introducing a capricious ERCOT permit process and shopping around for friendly solar projects to hop in bed with makes no sense when you can just write a check and solve the problem forever.

I'd bet the deal with Chevron was to enable Microsoft to hop the queue here and get those GEV turbines soonest.

1 comments

I'm not saying wait for an interconnection, I'm saying take a project that already has a fully developed plan, that's waiting for interconnection, and build the DC right there next to it, beef up the battery component of the plan and go to town. Interconnection happens some time in the future, giving far more financial opportunities for everyone, but in the interim the electricity goes fully to the DC.
Because I expect the economics of enough batteries to carry a data center’s worth of demand through the night and morning is too expensive compared to essentially free natural gas.

Data centers would ideally run at ~100% utilization, so any drop in solar output needs to be fully met by batteries.

> Data centers would ideally run at ~100% utilization

I don't think this is broadly accepted among major data center operators.

What makes you think you can change the facility that's in the ERCOT queue while keeping your place in line?