Meta's first five buildings took between two and three years to build, but Williams is almost done building out 200 MW (additional) off-grid power plants in a year, and to match that they're putting their equipment in tents. That raises questions for me: * Did they expect the next five buildings to also take between two and three years to build if done in the same manner? I'd hope it'd be significantly faster the second time because they've perfected the design, found good local contractors and suppliers, etc. * How much of the time was the actual structure vs. all the stuff inside they still have to do with the tents? * How long are they expecting to keep this? Are they anticipating extra problems like leaking roofs? * What are the "off-grid power plants"? Is this basically a whole bunch of diesel or natural gas generators? [edit: oh, yes, "The site is also powered by 200 megawatts of modular gas turbines". I wonder if they're trucking in the fuel too.] If so, yuck. |
|