No one's ever been able to explain story points to me without saying something like "Story points are kind of like how long it will take to implement, except it's not that". So what is it then? All the explanations and examples are in units of time, but with a disclaimer saying that the true nature of story points is not time-based, except for the fact that they can only be explained in terms of time. |
|
The managerial goal is to take near-past moving average rates (from completed tickets) and use them to forecast near-future expectations. 1.0 of Team Alpha's points might mean 4 hours this week... but anybody who shows up six months later expecting exactly the same rate is foolish, doubly-so if they expect it to be the same across teams, or after a big change in staff or tooling or project.
______
Other musings: Whenever a manager says "my current estimate of the rate is X pts/hr, use that when sizing", I feel it's a mistake. I kills off the intuition you really want to capture. Team members ought to be comparing expected tasks to past tasks.
Also, the goal of "accurate scheduling predictions" exists in conflict with "measure employee output". Trying to use your point-system for one generally harms the other.