by Huston1992
140 days ago
|
|
if i have to estimate something > 2 days i just assume im guessing. usually means there's hidden complexity i haven't found yet. i estimate until the subtasks are small enough (like 4h chunks), otherwise its all just feeling based numbers. |
|