What if the project involves trying one approach for a week, then assessing whether that approach still looks viable vs moving onto a different approach? This happens a lot with challenging projects, you basically just keep trying different things until one works. |
|
On the high end, could it take more than 2 years? 1 year? 6 months? Stop when you are 80% confident that it won't take longer than some period.
So your estimate might be between two weeks and six months. Is that an acceptable estimate for the "buyer"? If not, is it worth expending effort to narrow the estimate?