This is true, but the problem is that engineers are being asked to over-extrapolate given the evidence, and expected to own that extrapolation despite the paucity of evidence to make a good estimate. I *HATE* estimating roadmaps, because it feels unfair. I'm happy to estimate a sprint. |
|
I abandoned the plans from the previous PM and discussed the job with the developer who ballpark estimated that the work would take 2 months. After a quick analysis I adjusted this to 14 weeks.
But the account manager thought this sounded too long and insisted that we plug everything in to a Gantt chart, define the shit out of everything, map the dependencies, etc, which showed that the development would only take 6 weeks.
The project ended up taking 14 weeks.