by Moldoteck
145 days ago
|
|
I know about it, affected components were replaced. They still built it relatively on time and on budget "On 7 February 2014, the Nuclear Safety and Security Commission declared that its investigation since mid-2013, they found eight cases out of 2,075 samples of foreign manufactured reactor components that were supplied with fake documents." |
|
> relatively on time and on budget
Nope. 7 years late (plan: 2017, last reactor diverged in 2024).
Total cost not known, at least 24.5 billion USD and maybe up to 32 according to Bloomberg (plan: 20). Koreans are even fighting: KHNP (a subsidiary of KEPCO, the company building the plant) officially seeks for about 1.2 billion USD in compensation ( https://www.businesskorea.co.kr/news/articleView.html?idxno=... ) and it may worsen up.
Such a resounding success... as usual: https://www.fastcompany.com/90844859/why-massive-wind-and-so...