Civilian information systems have radically expanded in size since 2001, even if we take that ancient statement at face value. In the year 2025 it's crazy to believe that every newspaper is shouting that civilian information systems are destabilizing the national power grid and drying up the water table, but the government possesses a larger, far more capable information system that paradoxically has no observable physical presence. |
|
"The structure provides 1 to 1.5 million sq ft (93,000 to 139,000 m2), with 100,000 sq ft (9,300 m2) of data center space and more than 900,000 sq ft (84,000 m2) of technical support and administrative space."
"The completed facility is expected to require 65 megawatts of electricity, costing about $40 million per year. Given its open-evaporation-based cooling system, the facility is expected to use 1.7 million US gal (6,400 m3) of water per day.
An article by Forbes estimates the storage capacity as between 3 and 12 exabytes as of 2013, based on analysis of unclassified blueprints, but mentions Moore's Law, meaning that advances in technology could be expected to increase the capacity by orders of magnitude in the coming years."
https://en.wikipedia.org/wiki/Utah_Data_Center