Someone at the generation facility ran the numbers and found that the grid was able to dispose of excess energy for peanuts but installing and maintaining a dedicated electronic load cost more than peanuts. I'd recommend digging elsewhere for conspiracy bait. This is a mild curiosity at best. |
|
But I’m not sure that’s entirely correct, and maybe it’s time to revisit this.
Any system that is selling responsiveness as part of their service has to keep a certain amount of equipment sitting idle. That’s just how queuing theory works. So while you cannot move all server load to the coldest available zone, we should still be able to run that center near capacity and use the hottest one for all reserve capacity.
Power plants also have to deal with fines for exceeding emissions limits, but I suspect the problem here is that Bayesian analysis tells them that if a plant has to kick on early for some reason (early school release day, or another plant exceeded a maintenance window), it will still be needed for sure an hour from now, so it’s better to leave it running for 45 minutes doing nothing than to cycle it.