For us it was more like a 10x, but a few things went into that:
- We found screamin' deals on hardware by snatching it up when it was available, not when we needed it.
- We were at a fairly cheap colo, and haggled hard to get the cheapest rack possible. We went on a tour, noticed they had _tons_ of empty racks, and used that as some leverage.
- We didn't add any additional ops overhead by having everyone responsible for ops. We were in the 5k/month ballpark for EC2, and cut it to under $600 with a few grand outlay for hardware spread over the course of a quarter. That said, all of my current projects are on EC2 for the provisioning flexibility, and because I hate having to drive down to a datacenter at 4AM to swap a drive. |
|