by Dyac
580 days ago
|
|
If pushed, I get my developers to give estimates in jumps of ~5x. Their options are 2 days
2 weeks
2 months
10 months Then I triple the estimates before sharing with the business. We don't estimate individual tickets/bugs at all, just overarching projects. I also ask the business to estimate the commercial/user impact of the projects too, and we track and report the reality against their estimate, to hold a bit of a mirror up to them and as a way of pushing back on doing pointless work. Those estimates we use similar orders of magnitude for - £1k, £10k, £100k, £1m, £10m. Fermi estimations like these really help avoid protracted negotiations and the lack of precision is a feature that makes clear they are estimated. |
|