|
|
|
|
|
by rightbyte
580 days ago
|
|
Ye and this is the problem with management using estimates as deadline. When I was naive and believed that Agile was not a sinister micromanagement toolkit to mess with programmers, I tried to explain to people that about half of our estimates should overshoot and half undershoot or they are biased and that there should be more overshoots since there is no upper bound on how much time a task can take if the estimate is wrong. Ye. No. The burndown chart shouls be as straight as possible. |
|