by kragen
663 days ago
|
|
but 1.1 gigawatts of mainstream solar panels is 0.14 billion usd. $130 per kilowatt of capacity. even at the dismal 10% solar capacity factor achieved in very northerly countries like germany, the reactor is twice the price per average watt, and it needs to be installed far from the point of use—you can't buy a 440-watt nuclear reactor, so you need transmission, distribution, and transformers, all of which incur energy losses, capital investment, and safety hazards you can avoid with photovoltaic that large grid also needs regulation, billing, and political stability. (a reactor is an appealing target for both russian glide bombs and enron-style scams.) and the reactor is not dispatchable over timescales of less than a day, while you can short out a solar panel in microseconds fundamentally the reactor can't compete economically because it's shackled to a pricey steam engine. the reactor itself is a triviality, just a pile of fuel larger than the critical mass. some of them formed naturally at oklo billions of years ago. what's hard is integrating that energy release mechanism into a machine, and that's because the humans are still terrible at making machines |
|
A solar farm is more than just solar panels. This 3.5GW solar farm cost 2.13B USD, so by your estimates the panels make up just 1/5 of the cost of the farm. I'd expect the load factor of the nuclear power station to offset the solar farm's nameplate capacity advantage, and lead to steadier prices/fewer storage requirements etc etc.
https://www.pv-magazine.com/2024/06/06/worlds-largest-solar-...
> and it needs to be installed far from the point of use
Note that this is a problem for solar farms in China; they are installed where land is not valuable. Hence all the HVDC transmission records being broken in China. Plus nuclear power stations can be close to populations. For instance https://en.wikipedia.org/wiki/Daya_Bay_Nuclear_Power_Plant is 50km from Hong Kong.
> the reactor is not dispatchable over timescales of less than a day
Modern reactors have load following capabilities, e.g. the AP1000 can ramp up 5% a minute within the 15%-100% band.