by psunavy03
779 days ago
|
|
But if you're doing Monte Carlo, you might as well just iterate and keep re-running the Monte Carlo as you burn through the backlog, because that's a better way of having up-to-date information that using any kind of Gantt chart. |
|
If you have a backlog, and you don't mark what is dependent on what (in progress or also in the backlog) you're just hurting yourself. Once you add that information and some very basic estimation (even just scale of expected effort is enough) you can generate a Gantt chart and use Monte Carlo simulations to get an understanding of your time estimates.