Incredibly false. A typical "large" rig will need a 100m x 100m drill pad, roads to access which are often highly controlled during the design phase. A drilling rig will remain on location for MAYBE 30-40 days if it is a deep well (2000m-7000m). A completions rig (aka service rig) will come out afterwards to complete the well (install downhole equipment / frac / get the well ready for production).
Lease may be a bit bigger if large frac. Been a drilling engineer for 15+ years so haven't really seen too many fracs. |
|
I can imagine in a big oil field like in Midland, TX they have a lot of sprawling operations that take up a lot of room. But that doesn’t have to be the only way.