by throwaway9191aa
933 days ago
|
|
Our team had so many planning poker sessions where we spent 12 people * 2 dev hours trying to figure out whether stories were a 2 or a 3, management finally said it is always a 3. We were literally spending more aggregate time trying to decide effort, than the actual effort it took to complete these tasks. 2 and 3 are equal. 5 and 8 are equal. The question is simply "Is this a couple days, the whole week, or the whole sprint?". |
|
+ That's trivial, it will be ready for testing before lunch.
+ I know how to do that, should be ready tomorrow/next day.
+ I can see how to do that but there are lots of other constraints - at least a week, might be more.
+ It's a big project, needs more planning and specification before it becomes a series of estimable tasks. Let's do that.
+ That breaks other things we care about. We need to prioritize and be ready for rework.
If you want, you can call these small, medium and large.