by meheleventyone
953 days ago
|
|
I work with a team from PT->CET and am in UTC-0 so no joke the first thirty minutes to an hour of my day is catching up with the rest of what happened the previous day and what’s going on at the start of the next day. I don’t need to schedule it because thankfully my morning is usually quiet but it’s common enough I mention it in my work log. I don’t think this is unplanned work so much as unrecognised work. Few Gantt charts etc. keep track of that overhead like the overhead from ‘surprise’ tasks. |
|