by Crye
969 days ago
|
|
Yes and no, 1200km charged in 10 mins is somewhere around 1MW of peak load. that's manageable and readily available using off the shelf distribution equipment, but it is a lot. The equipment is by no means cheap and large charging sites would almost always require upstream distribution and transmission upgrades, but this is something utilities are planning for. I suspect we'll also start to see on site energy storage to help offset the demand charges that these sites could see. |
|