by pyrale
1104 days ago
|
|
Not sure how you read that in the graph. What I read: model : first reactor -> last reactor
CP0 : 65 months -> 60 months
CP1 : 73 months -> 64 months
CP2: 56 months -> 79 months
P4: 82 months -> 74 months
P'4: 85 months -> 89 months
N4: 151 months -> 104 months
That's 2-3rds of the builds showing a speedup. The results are even more striking if you calculate the correlation between start date and build time for any 2 reactors of the same model. |
|
Yes, I considered the long-term experience gain (columns, not lines: from 65 to 151 and from 60 to 104).
The first nuclear plants were theoretically the most difficult to build as the local industry was less adjusted to building such things, especially specific components.
As those reactor 'models' were very similar (there is no quantum leap) pertinent experience (processes, tooling...) accumulated.
However there was no reduction of 'intensity' (investments, amount of simultaneous building projects, foreseeable projects...) as all this was encompassed by a huge national programme (the 'Plan Messmer').
Therefore it seems that both min and max time to completion should diminish with time.