You can calculate the team velocity pretty easily in Scrum (amount of story points completed per sprint) and from that you can estimate what gets done in what time. BUT it needs the exact same team to be together on the same codebase. You add or remove people, the velocity changes. You change projects, velocity changes. People also need to be honest when estimating tasks, don't be a 10x cowboy and say something is a half-day task when you know it'll take two days. It's always better to pick too few tasks for a sprint than it is to take too many. You can always grab more stuff off the project backlog if the sprint backlog runs out mid-sprint. |
|