by mikeyouse
1175 days ago
|
|
> The only difference in cost for the plant to exist and not run but be ready and to run is the cost of the fuel. Which is over 50% of the cost of running a combined cycle plant (page 12: https://www.lazard.com/media/sptlfats/lazards-levelized-cost...) -- but also misses that you'd need far fewer plants if you build renewable + storage generation to match the 99% use case so the total cost spend on peakers would drop dramatically even if some were still needed to provide backup generation. Also has the added benefit of almost entirely decarbonizing power generation. |
|