by acdha
1189 days ago
|
|
I’m pretty sure he’s aware of which country Copenhagen is in but was simply pointing out as an example a much harder large, complex project in a dense urban environment built in far less time. The key thing to understand is that while other countries have some boondoggles, the United States does almost nothing else despite spending massive amounts of money. The Purple Line mentioned was ostensibly going to be cheaper due to a public-private partnership but that ended in delays and greater costs as those almost always do, and the same was true of a highway expansion Maryland was trying to do with an Australian partner, and just about every other major American road, rail, bridge, bus station, etc. project is similar. Even our bike lanes take ages to build for the relatively small amount of work. I agree with the theory that much of this is due to hollowing out the civil service as a “cost savings” measure – these projects sound like what I’ve seen at large organizations where they want a software project without hiring developers so they bring in one consulting company to do the work, and after the first round of failures, a second to oversee the first. Even if everyone is actually acting in good faith it’s just inefficient when you have multiple parties and difficulties sharing or acting on institutional knowledge. |
|
One World Trade Center a public/private partnership started construction April 27, 2006 and opened on November 3, 2014 at the cost of 3.9 billion. Which is easily in line with similar projects around the world, even though it was much slower than such projects back in the 1920’s.
It’s a more complicated building than those 1920’s designs booth from modern standards + features like AC, but also because it was designed to survive an attack.
PS: The Copenhagen Metro has been a 28+ year project that’s gone well but it’s hardly that amazing on its own. Planning began in 1992, the first construction started in 1996, first line opened in 2002 and the project is still continuing with only 12.7 miles in operation. By comparison the DC metro system is currently 129 miles long of which about 50 miles are underground with construction starting in December 9, 1969 and the first 4.6 mile segment opening in March 27, 1976.