Even slow overnight charging will have to be pretty beefy for these trucks and their batteries though. They're going to expend significantly more energy than your commuter car so they'll have to suck down a lot of juice overnight. |
|
Just to put some numbers out there, the semi battery pack is probably around 850kWh-1MWh. Imagine if this gets drained every day and a company has 10 trucks, the trucks have roughly 10-12 hours to charge (~6pm to 6am). So you'd need 1MW of electrical capacity.
This is equivalent to about 20 modern US homes (200A*240VAC) and not that crazy in the scheme of things. A medium sized factory in the US probably has a grid connection around this size depending on what they do.