by iancmceachern
1524 days ago
|
|
I once worked on a project with a steep late delivery penalty. We had already scheduled a "hit shot" truck, which is a dedicated semi, usually a team of 2 drivers, that drives directly, no stops, to the destination. We had scheduled it and it was 3 or 4 days to get from Denver to NYC. We were late, frantically building and assembling hardware and so just weren't ready when the truck came. We shipped the large pieces, large empty stainless steel shells in a mostly empty truck. We then took the extra 2 days to assemble the rest of the hardware and air freighted it at $50k extra cost and 1 day to get there. Basically we bought 2 days on the project for $50k and just barely made our delivery deadline. |
|