Hacker News new | ask | show | jobs
by chiph 1655 days ago
I remember when he made that post ("Evidence Based Scheduling"), and was also appalled. Yet, here we are today and programmer velocity is a now a measured metric in Agile.

https://www.joelonsoftware.com/2007/10/26/evidence-based-sch...

1 comments

Oh ye thank you that is the one.

The general problem with Scrum like velocity tracking is that devs will start to lie to hit the estimates to keep the commissars of their backs. The best liar gets the straightest graph. And as devs learns to lie, you get the impression of improved estimation.

"Some developers (like Milton in this picture) may be causing problems because their ship dates are so uncertain: they need to work on learning to estimate better."

I mean ... why God. I don't know but maybe poor Milton has the hardest tasks, does not cut corners or what not. Brandon seems to "get it" and has silly narrow error range - I wonder how ...

(I am not bitter. Pinky swear)