Monthly generator testing is, and should be, standard for any data center. Same with the UPSes - monthly testing to make sure they can handle the load long enough for the generators to kick in. Throwing the switch on the mains is probably not happening anywhere on a regular basis, though. There may be "routine" events (some sort of electrical infrastructure upgrade) that causes the data center to be put onto generator power, but throwing the mains just to test is a very risky endeavor, and one that a data center provider who has very high power availability guarantees with expensive penalties, is not like likely to undertake. |
|