by tiagogm
1815 days ago
|
|
True, I do find it easier and a less time consuming to break a large piece of work in around 2day chunks (for example) than using different sizes or trying to decide if something is 3 or 5. In the end, regardless of whatever scoring strategy you use it should always be team centric, rather than individual. It is possible to say, over the past 6 months, and X tickets, our team has had a Median/Avg cycle of around 2days. If team breaks future work in similar sized chunks, it can very fairly confidently predict how long they will take to do X more tickets, assuming similar conditions. The added benefit of using small chunks of time, is that one does not need to be super accurate (in most scenarios), it can be 1 or 4 days, all it matters is it's possible to give window of estimation (based on actual data, not guesses) with a certain degree of confidence. (which will naturally become even more consistent over time) |
|