Hacker News new | ask | show | jobs
by ac29 1873 days ago
I'm pretty cynical myself, but the first phase of BART extension to the south bay is already completed and has been running for nearly a year, and cost $2.9B. The second phase is a bit more difficult because it requires substantially more underground work in downtown San Jose, but $40B would be quite a bit even by CA standards.
1 comments

Madrid does all underground lines lines like your phase 2 for about 1 billion. Someone needs to learn about cost control. Think of how much more they could get with Madrid prices.
Not saying that CA prices aren't inflated, but there are also geological differences that probably matter. Madrid isn't near active fault lines (not to mention generic soil differences that can matter, but IDK if they do in this case).
I don't have Japanese costs, but they are lower, and deal with worse earthquakes than CA