You seem to have omitted the part of the model that would explain why you want the price to be higher. You specify that > your region's generators are only able to supply 75GW of power maximum no matter what price you offer. Want 100GW all you like, you won't get there. What are you trying to accomplish? |
|
If your legislature (not to mention local culture) has insisted you must only use a hammer, those screws are getting hammered in, too bad.
If you have greater import/export capacity the higher prices ensure you're importing. In this particular case that would likely have made no difference, it's not as though the storm was just affecting Texas, but in other cases or with a smaller deficit that might save your backside.
Also as I understand it, some places pay generators for their capacity to deliver power if it were needed, even if in fact they're never needed. So that can be a better plan because it makes the incentive not to fail clearer.