he also links to a conference talk about this. "you can make a claim that estimates are based on past behavior, but the fact is that what you're implementing is something that hasn't been implemented before. So any kind of measurement that you've made of something that has happened in the past is not going to impact what you're doing now" https://www.youtube.com/watch?v=QVBlnCTu9Ms |
|
For a concrete example, let's imagine a team which has a continuous delivery pipeline which involves a code review step and manual acceptance tests. Let's say that the code review can stay in a queue for a couple of hours, or even sleep into the next day, and that the manual acceptance tests require the feature to be deployed to a preprod stage after passing through all unit and integration tests, and that it might take a day to run.
With this process alone, the ticket already takes at least 2 or 3 days between being assigned to someone and being marked as done.
Now, let's say that the coding bit of a random ticket might take 5 minutes or 3 days. This means that the overall time between the start and end time of a ticket is about 4 days +- 2day, which means worse case scenario, it takes 6 days to close a ticket.
How is this sort of estimate not possible?
The problem of providing estimates is not one of predicting the amount of time it takes to close a ticket. The problem of providing estimates is a problem of processes, and how to adequately organize, structure, and classify work. If you don't know what you're doing then you don't know when you're done.