Starting at the very next sentence in the article:

> From what I can see, ERCOT has more restrictive rules in their Generator Winter Weatherization Workshop than NERC[21]. All generation stations must have plans for emergencies, address abnormal weather, critical failure points, weather design limits, alternative fuels and testing[21,22]. ERCOT reports that there were 80 spot checks done in the 2019/2020 season with 71 being gas plants and 6 being black start gas plants. 23 had to improve and would be reinspected in early 2021 the rest passed.

This directly refutes your claims that "there are no winterization standards" and "There are merely recommendations, none of which were implemented by ERCOT." The inadequacy of NERC is irrelevant to ERCOT.