by pfdietz
2077 days ago
|
|
NuScale has given up assembling their reactors in their factory. https://losalamosreporter.com/2020/08/22/get-out-of-the-fluo... "In answer to a question I posed to Nuscale at the town hall we have learned that the plan to save costs by fabricating the modules at a remote factory and shipping them to the Idaho site has been abandoned. The artful response to my question said that Nuscale engaged with approximately 40 … pressure vessel fabricators worldwide and … determined that Nuscale will use existing factories … in lieu of building its own factory. The major module subcomponents will be manufactured at multiple manufacturer locations and shipped to a single location for assembly prior to installing into the facility.” This signifies the failure of one of the major cost-saving features of the Nuscale project, which was to forestall this exact scenario." The cost of that project has already escalated 70%, btw, with three towns dropping out and the output only 30% subscribed. I think there's a good chance it will never be built. |
|