by sharken
2119 days ago
|
|
As someone who is again at a company doing SAFe, I am genuinely curious as to the relevance of story points. For estimation, hours is a good measure, even more so when there are external consultants that get paid by the hour. Developer velocity can be measured by tasks/features completed compared to the estimate. Could you elaborate on why story points are useful or perhaps point to some resources on the topic ? |
|
There was an expectation that devs complete about 8 points a sprint. I don't know if the eight point target is common, but SAFe does talk about comparing story points across teams.
> At scale, it becomes difficult to predict the story point size for larger epics and features when team velocities can vary wildly. To overcome this, SAFe teams initially calibrate a starting story point baseline where one story point is defined roughly the same across all teams.
...
> Give every developer-tester on the team eight points for a two-week iteration
https://www.scaledagileframework.com/story/