by porker
2604 days ago
|
|
I'm struggling with this advice, and thinking either the projects you scoped, or the scope itself, are different to what I have in mind. Can you expand on the type of projects you would do scoping for free for? Last year I spent 2 and a bit weeks doing paid scoping, because the client knew where they wanted to get (replace a legacy system), didn't know how it worked, didn't know how their business process was structured. Short of a value-based pitch (which has failed with them in the past) the alternative was a guess. Afterwards we agreed to go onto build the new system. [ There's a whole 'nother side story as I'd lost money on every project I'd done with them before, so this time opted for time & materials - which sort-of worked, but as their max budget was fixed, as was much of the scope, resulted in considerable stress. Still looking for the lesson to learn. ] |
|
Spend as much time as you think you need to come up with an educated guess.
Build a proposal that quotes a fixed time for the project, but bill the project T&M. Include in your proposal a provision for overage, pro-rated at a daily rate.
Don't bill for scoping work. If it takes 2 weeks to scope your typical project, and those 2 weeks are dragging your practice down, what I'm hearing is that you should raise your rates on delivery, not that you should try to charge some secondary "discovery" rate for or (god forbid) try to bill at your delivery rate.