> Trouble is, businesses/clients tend to see an estimate as a promise, or a target Even worse, they tend to treat the date/cost line as a promise, but the scope as infinitely flexible. One other thing that makes me crazy is that a lot of places determine the date by a process that yields the first non-impossible date. (E.g., "Can this be done by Thanksgiving?" Developer yelps and says, "Well, maybe if everything goes right it could be done by Christmas." The PM responds, "Great! Christmas it is! I'll tell the CEO.") But if non-impossible means, say, 5% chance of success, then the developers look like goats 95% of the time. These days, except with highly trusted partners, I basically refuse to estimate anything over 3 days without formal estimation and a self-calibrating process where any date is a function of product manager choices. (E.g., points, velocity, burndown.) But I find that less and less valuable, as interesting projects typically have requirements volatility too high to make dates actually predictable. Instead I prefer a release-early, release-often approach, hitting any non-artificial deadlines by being ready well in advance and iterating. |