You need to separate the R & D. The research is unknown and you can't estimate. The development is known, and if you can use prior experience to estimate. Give estimates in DURATION never as a date. Treat it as a stop watch, anytime interruption happens, the stop watch stops. So 2 weeks can actually take 6 actual weeks. If there's no research and interruption, then you should be able to give a +/- 10% estimate. |
|
Do you have any experience/advice for R&D estimates? This is something I struggle with alot. We try to bill per _project_ rather than per _hour_, but I'm thinking R&D perhaps necessitates hourly billing, which sucks.