Waiting to be back in sync could take forever, plus you need a Sync Check Relay. Price of those is usually "contact sales team" and they don't work reliably if you don't need more than a couple dozen kW of power. (They're intended for 1MW+ installations). Just shut it down, flip the switch and restart. Everything else will just be prohibitively expensive because it needs to be very safe. If you get the phase wrong then you'll either reduce the lifetime of your components or the components explode after the nearest power plant tries to pump all available power into your poor inverter. |
|
Only if you design it to. The phase locked loop would "listen" to the mains frequency and slew to match. Slew speed is simply a design parameter you can set to any value.