by tzs
2902 days ago
|
|
From the first:> Shane Co. signed a contract with SAP AG in 2005 for a "highly sophisticated point-of-sale and inventory management system," with an original projected cost of $8 million to $10 million and a one-year rollout schedule, the filing states. But costs ended up skyrocketing to $36 million, and the implementation stretched out to 32 months before the ERP system eventually went live in September 2007. Does anyone offer SAP rollout insurance? |
|