|
|
|
|
|
by shagie
3042 days ago
|
|
An estimate is not a single number. Rather, an estimate says “it may take 1h if everything goes well, it may take 16h if things go bad.” This is then followed up with “at 1h, I’ll update with either a done or a revised estimate.” Giving single numbers for an estimate with uncertainty is bad for all parties. Additionally, with experience one can get better at giving estimates with less uncertainty for well known tasks and recognize the uncertainty for other tasks. |
|
AKA Y is much higher when you deal with low hour estimates.
This is most noticeable when you have lot's of tasks. If you think 200 tiny tasks may take 1 month or just over 1 year that's an almost useless estimate.