by afarrell
3323 days ago
|
|
> Measure timeliness with respect to estimates What if you have an employee who doesn't know how to do software estimation? Do you know of ways to teach people how to do estimates or resources/habits they can follow to learn how to estimate how long tasks will take? I ask this as someone who has only received the advice "go with your gut and triple it." There is a book by Steve McConnell on estimating larger projects but nothing out there on estimating things within a week. |
|
If the problem is in fact known, your estimate will be the time to pull in a library from GitHub. If it's not to pull in a library, you're into unknowns.
Asking to estimate may work in aggregate if your 'gut' is good at assessing the amount of unknown your devs' face (e.g., 2x as much unknown work - multiply estimate by 3), but not in the specific. The specific amount of unknowns in a given task are unknown.
To translate a requirement into code will take exactly as long as it takes to discover and bridge the unknowns. You can't do anything about that, other than (a) change the requirement, or (b) change how much is known by the developer.